The overlaying and welding processes for NPP equipment units in Turkey have been launched at Atommash.

Дата публикации: 19-06-2018 06:25:00

The Volgodonsk Branch of JSC “Mechanical Engineering Division-technology” (a part of Machine Building Division of Rosatom- “Atomenergomash”) proceeded to the overlaying and welding of the equipment units for Akkuyu NPP in Turkey. The Turkish Nuclear Power Agency (TAEK) approved the beginning of the production.

Основное содержимое страницы с новостью.

image

The Volgodonsk Branch of JSC “Mechanical Engineering Division-technology” (a part of Machine Building Division of Rosatom- “Atomenergomash”) proceeded to the overlaying and welding of the equipment units for Akkuyu NPP in Turkey. The Turkish Nuclear Power Agency (TAEK) approved the beginning of the production.

The TAEK representatives and plant building operators – company JSC “Akkuyu Nuclear” - carried out the conformity assessment of the reactor and steam generator parts at Atommash, earlier passed to production for machining. Visual and dimensional inspection of the finished items has been performed on a selective basis.

The inspectors also assessed the readiness of the Volgodonsk Branch of JSC “Mechanical Engineering Division-technology” for the beginning of the overlaying and welding works on the parts and assembly units of the reactor vessel and steam generators for the power unit No.1 of the Turkish NPP. Foreign colleagues checked the readiness of the process equipment and the measurement assurance, the availability of the qualified personnel, the design and process documentation and activities on quality assurance.

It has been established, based on the inspection of TAEK and JSC “Akkuyu Nuclear” that Atommash can procced to the overlaying and welding works on assembly units of the equipment for Akkuyu NPP: upper, lower semi-vessels of the reactor vessel and the cover of the upper unit, and also on the shells and head.

“Akkuyu” NPP in Turkey is being built according to the modernized project with the power units of IIId generation, with the increased safety and enhanced technical and economical characteristics. JSC “Atomenergomash” is a single source manufacturer and supplier of the power unit equipment and power house for all four units of the NPP. The reactors, steam generators, pumping, heat exchange and other equipment shall be produced by the enterprises of the Division that will ensure the NPP safety for overall plant service life.

Назад

Схожие новости

#Наименование новостиТональностьИнформативностьДата публикации
1WELDING OF THE REACTOR COVER FOR AKKUYU NPP IN TURKEY COMPLETED AT ATOMMASH04.8222-01-2020
2WELDING OF THE REACTOR COVER FOR AKKUYU NPP IN TURKEY COMPLETED AT ATOMMASH04.8204-12-2019
3Check assembly of the reactor for the first power unit of Akkuyu NPP has been started at Atommash06.1609-09-2020
4Volgodonsk and Petrozavodsk Branches has proceeded to manufacture the equipment for Akkuyu NPP in Turkey07.3307-12-2017
5“Atomenergomash” performed the final weld on the Reactor Pressure Vessel for “Akkuyu” NPP07.5212-02-2020
6Atommash is manufacturing the first reactor bottom for Akkuyu NPP in Turkey010.7221-01-2019
7Atommash has manufactured the reactor cover for the First Unit of Akkuyu NPP (Turkey)0630-11-2020
8Atommash completed key stage in manufacture of bottom of nuclear reactor for Unit 3 of “Akkuyu NPP”09.6707-09-2021
9Atommash has shipped equipment for the first reactor of the "Akkuyu" NPP07.8528-04-2021
10JSC “AEM-TECHNOLOGY” HAS OBTAINED MANUFACTURER APPROVAL CERTIFICATE FROM TURKISH ATOMIC ENERGY AUTHORITY014.1212-10-2017

Классификация: В стране. Схожих патентов: 0. Схожих новостей: 10. Тональность: 0. Информативность: 5.81. Источник: www.aem-group.ru.