Bangalore Metro Pink Line misses 15th Aug deadline despite RDSO’s approval for rolling stock

Дата публикации: 14-08-2026 10:45:00

BANGALORE (Metro Rail News): Bangalore Metro Rail Corporation Limited (BMRCL) has received the interim speed certificate from Research, Design and Standards Organisation (RDSO) for the rolling stock of the upcoming Pink Line. This certification came after the successful execution of the necessary trials on the Pink Line from Kalena Agrahara to Tavarekere on Wednesday (12th […]

Основное содержимое страницы с новостью.

Bangalore Metro Pink Line misses 15th Aug deadline despite RDSO’s approval for rolling stockRepresentational Image

BANGALORE (Metro Rail News): Bangalore Metro Rail Corporation Limited (BMRCL) has received the interim speed certificate from Research, Design and Standards Organisation (RDSO) for the rolling stock of the upcoming Pink Line. This certification came after the successful execution of the necessary trials on the Pink Line from Kalena Agrahara to Tavarekere on Wednesday (12th August). Despite this the Pink Line has missed the deadline for 15th August. The project is now expected to open soon after the CMRS inspection.

The Chief Public Relation Officer (CPRO) of BMRCL informed on Thursday (13th August) that the new rolling stock of the pink line has gone through the Oscillation and Emergency Brake Distance Trial. The trials were successfully conducted and the RDSO granted the interim speed certification for the rolling stock.

As per an earlier confirmation, BMRCL has received eight trainsets for the pink line from BEML. They have planned to start operations with 3-4 trains in the beginning and gradually add more rolling stock.

This certification has paved the way for receiving the railway board sanction for the new rolling stock supplied by BEML. After the issue of certification, the Commissioner of Metro Rail Safety (CMRS) will inspect the rolling stocks and the overall safety standards, following which it will authorize the opening of the elevated pink line for passengers.

The weekly brief metro & rail professionals read.

Bangalore Metro’s Pink line is under the Namma Metro phase II project. The pink line will connect Kalena Agrahara to Nagwara. At present, the elevated stretch of the line from Kalena Agrahara to Tavarekere is expected to open soon while the underground stretch from Dairy Circle to Nagwara is under construction. 

Also ReadBangalore Metro Pink & Blue Lines Receive Fresh Deadlines under New Leadership 

Guide
Bengaluru Metro: the complete guideAll corridors, status, routes and the latest news in one place →

Схожие новости

#Наименование новостиТональностьИнформативностьДата публикации
1Railway Board Gives In-Principle CBTC Nod for Bengaluru Metro Pink & Blue Lines016.2510-08-2026
2 Comment on Bengaluru Metro to connect Tamil Nadu Border: BMRCL plans 9 new stations  by Satish 013.6717-08-2026
3 Comment on Bengaluru-Mumbai Vande Bharat Sleeper moves closer to launch with arrival of trainsets by Narendra Shah 09.4614-08-2026
4Big Breakthrough for Kolkata Metro’s Purple Line as TBM Divya Reaches Victoria Metro Station 015.5812-08-2026
5Chennai Water Metro: CMRL floated tender for DPR along Buckingham Canal016.813-08-2026
6Goa Infrastructure Boost: RVNL signed MoU as Project Executing Agency027.0920-07-2026
7MMRDA grants signage contract to CBM Industrie for Mumbai Metro Line 2B 017.1112-08-2026
8India on the Move: Revisiting the milestones in Railway, Metro & RRTS on the 80th Independence Day015.2815-08-2026
9Kasheli Depot for Mumbai Metro Line 5 Achieves 23% Physical Progress022.1222-07-2026
10Flying Train: China’s Ultra-High Speed Train reaches 800 kmph in 5.3 seconds023.2417-08-2026

Классификация: . Схожих патентов: 0. Схожих новостей: 10. Тональность: 0. Информативность: 14.82. Источник: www.metrorailnews.in.