Oracle’s Project Jupiter delay sends ripple through AI financing

Дата публикации: 25-09-2026 04:53:19

Companies can use force majeure provisions when events beyond their control make ‌it ⁠difficult to meet their contractual obligations

Основное содержимое страницы с новостью.

Oracle’s move to protect itself against potential delays at a massive data centre project ‌developed by Blue Owl in New Mexico sent a chill through the trillion-dollar market for AI ​infrastructure financing, according to interviews with bankers and investors.

Oracle issued a force majeure notice in connection with Jupiter, ⁠a data centre campus Blue Owl unit STACK Infrastructure is building to support OpenAI, the latest setback for a sector where lenders and investors are growing more cautious about financing the industry’s breakneck expansion.

Blue Owl said the notice did not alter the parties’ commitment to the ‌project. Even so, the event is reverberating through discussions around other proposed data centre financings, including SB Energy, which is developing a campus to serve OpenAI in Ohio, a person close to its financing said. SB Energy ‌decided this week to delay its IPO.

Companies can use force majeure provisions when events beyond their control make ‌it ⁠difficult to meet their contractual obligations. Lawyers say such provisions are becoming more common in data centre development ⁠agreements, raising concerns among lenders and investors.

“The financing side of the AI buildout is starting to ask much harder questions than the demand side,” said Sean McDevitt, a partner at management consulting firm Arthur D. Little. “The underlying demand still appears very strong, but investors and lenders are increasingly focused on how ​risk is allocated.”

With interest rates in the US ‌rising to levels last seen two decades ago, Wall Street is intensifying its scrutiny of the economics and the politics of deals that just months ago appeared settled — meaning that the participation in a deal of highly rated firms such as Oracle isn’t necessarily enough to soothe anxious investors.

The pullback comes as AI-related capital spending by the six biggest US ‌technology companies is projected to reach around $1 trillion in 2027, according to Moody’s — raising concerns among lenders about ​whether markets can absorb the volume of issuance without wider pricing pressure or tighter terms.

Investors and lenders are studying the Oracle situation as a real-world example of how contractual protections may ⁠be tested and who pays the bill when projects run into delays outside the parties’ control, they said.

The program is being delayed by a year, said the person familiar with Oracle’s notice and the deal. Blue Owl has about $3 billion of equity invested ‌in the project and earns a lower return during construction, with returns increasing once the data centre is completed, the person familiar with the terms said.

Oracle invoked force majeure due to delays securing power to the site, the person familiar with the matter said. Delaying completion pushes back the start of those higher returns for Blue Owl.

As developers race to build AI infrastructure at unprecedented scale, the contracts underpinning those projects are changing quickly, said Rajat Rana, a New York-based partner at law firm Quinn Emanuel.

“These contracts are so rapidly evolving. If you look at a data center contract from January this year and a ‌contract today, it’s massively different,” he said.

At least 45 projects worth $68 billion faced opposition from community groups in the second quarter of 2026, according to research ​firm Data Center Watch, after 75 projects worth about $130 billion were disrupted in the first quarter. Banks are involved in several projects that face community action.

Earlier this year, Blue Owl struggled to ⁠syndicate financing for a $4 billion data centre project in Lancaster, Pennsylvania, anchored by CoreWeave.

“Blue Owl, STACK Infrastructure and Oracle remain fully aligned on ⁠Project Jupiter. This notice does not change the financial commitments to this multiyear project,” the company said.

Oracle stock fell 3.5% on Thursday, after media reports of the notice. Blue Owl closed 3.6% lower.

Data centre developments including Meta’s ‌project in El Paso, Texas, and Related Digital’s planned $16 billion Oracle-focused campus in Saline Township, Michigan, have faced opposition from residents of those areas.

Blackstone’s QTS in July said it had terminated its planned Digital Gateway data centre project in Virginia ​and withdrawn the associated filings after years of planning and regulatory review.

Схожие новости

#Наименование новостиТональностьИнформативностьДата публикации
1Oracle's $18 billion data center debt under pressure: FT 012.4919-09-2026
2Oracle to slash more jobs to fund AI plans with ‘double digit’ percentage cuts on some teams: report010.8912-08-2026
3Hyperscaler AI borrowing binge shakes up foreign credit markets08.114-08-2026
4Indian AI startups confront new risks after Anthropic pulls Fable 50515-06-2026
5SenseTime: US blacklist threatens to stunt growth of China’s biggest AI company 012.9410-12-2021
6AI’s volatile power demand is damaging its own data centers 08.610-08-2026
7Risk management firm Optro opens Singapore hub013.7725-06-2026
8AI influx puts Singapore office rents under pressure01020-09-2026
9Válságban az Oracle gigantikus adatközpont-építési projektje012.4925-09-2026
10 Why Anthropic and OpenAI are locking up their latest models 0515-04-2026

Классификация: Пресс-релизы. Схожих патентов: 0. Схожих новостей: 10. Тональность: 0. Информативность: 9.3. Источник: www.thehindu.com.